Advanced Projects Under Development

McKelvie Creek Hydro Project

Located near Tahsis, BC, on Vancouver Island, the proposed McKelvie Project would provide 5.2 MW of run-of-river power. Both a water license and land tenure have been issued from the Province of British Columbia.

Newcastle Creek Hydro Project

The Newcastle Hydro Project is to be located on Newcastle Creek on Vancouver Island near the Village of Sayward. It has a proposed installed capacity of 4.3 MW. Synex Energy is continuing to advance the regulatory aspects of this project. Both a water licence and land tenure have been issued from the Province of British Columbia.

Victoria Lake Hydro Project

Located 7km southeast of Port Alice, BC, on Vancouver Island, this proposed project would provide 10 – 15MW of power and has lake storage available. The Victoria Lake Limited Partnership, owned by Synex Energy Resources Ltd. and another energy developer, is the owner and proponent of the project.

Other Development Projects

Development Sites
Site NamePower (MW)
Montague3.4
Victoria Lake9.9
Ucona12
Newcastle4.3
McKelvie3.4
Exstew – Unnamed Trib 29.5
Exstew – Unnamed Trib 310
Exstew River37.4
Exstew – Unnamed Trib 47
Exstew – Unnamed Trib 4B8.4
Exstew – Unnamed Trib 510.5
ZZ Creek – West of Terrace14.9
Racoon Creek18.5
Klite River18.8
Seshal Creek17.9
Ayton4.3
Khtada15.2
Potential Total Power205.4 MW